How to build a house in Pakistan, from plot to handover

The whole build in order: what happens at each stage, what you decide and by when, which documents you hold at the end of each, and which mistakes cost the most. Start here, then open the detailed guide for the stage you are at.

Reading time
15 min
Chapters
11
Checklists
4
Last checked
October 2026

Who this is for

  • First-time builders planning a house on a plot they own or are about to buy
  • Families who have started and want to check the order of what they are doing
  • Anyone who wants to know what to ask, and when

Have to hand

  • A rough idea of your budget, and what you need from the house
  • A plot, or a shortlist of plots
  • Time to make decisions on a schedule

You will finish with

  • The ten stages of a build, in order, with what you hold at the end of each
  • A decision calendar for the choices that cause the most delay
  • The ten mistakes that cost most, and how to avoid each
Chapter 1

The whole journey at a glance

See the ten stages in order, and what you must have in hand before moving to the next.

Building a house is a sequence in which each stage depends on the one before. The sequence matters more than any single stage, because a step done out of order (ordering steel before the drawings are approved, tiling before the waterproofing test) is where money is lost. The table is the map for the rest of this guide.

The ten stages
StageWhat happensYou hold at the endDetailed guide
1. Brief and budgetDecide what you need and what you can spendA written brief and a budget with a contingencyBudget and BOQ
2. PlotChoose, verify and buy the landVerified title in your name; plot dimensions in feetBuying a plot
3. DesignArchitect and engineer prepare drawingsArchitectural, structural and services drawingsThis guide, chapter 4
4. ApprovalThe authority approves the planStamped, approved drawingsMap approval
5. TenderContractors price the same BOQ; you chooseCompared bids and a chosen contractorHiring a contractor
6. Contract and startSign the contract, set up the siteA signed contract, payment schedule and programmeHiring a contractor
7. Grey structureFoundation, frame, slabs, walls, roofA shell, with every hold point inspected and recordedInspection
8. ServicesElectrical, plumbing, drainage, waterproofingTested services and a tested waterproofingInspection, Waterproofing
9. FinishingPlaster, floors, joinery, paint, fixturesA finished house and a snag listInspection
10. HandoverSnagging, documents, completion certificate, defects periodCompletion certificate, as-built drawings, warrantiesThis guide, chapter 10
Chapter 2

Stage 1: your brief and your budget

Write down what the house must do and what you can spend, before looking at a single plan.

Most disappointment comes from a gap between what the owner wanted and what they asked for. Writing a brief takes an evening and saves months of drawings that miss the point.

Your brief

0 of 11 done

Then set the money. Decide the most you can spend in total, list every cost head (not only the contractor’s price), and hold a contingency. The cost and BOQ guide has the cost-head table, the method for getting a rate from real quotes and the contingency advice.

Chapter 3

Stage 2: the plot

Buy a plot you have verified, and know how big it really is.

You can fix a bad design. You cannot easily fix a bad title. Verify the plot before you pay, and before you spend on design.

  • Work from the plot’s dimensions in feet, not only in marla, because the marla differs between places. Use the plot size calculator.
  • Verify the seller, the ownership record, the chain of title, the scheme’s approval and the dues, at the source and not through the dealer.
  • Visit the plot and check the boundaries, access, level, neighbours and services.
  • Pay in stages by bank transfer to the owner’s own account, and complete the registration and the transfer before the balance is paid.

The full sequence, with the document checklist, red flags and the agreement checklist, is in How to buy a plot in Pakistan without being cheated.

Checks for the builder, not the buyer

Beyond ownership, look at the plot as someone who will build on it:

The plot as a building site

0 of 9 done
Chapter 4

Stage 3: design

Get a complete set of drawings, and know which ones to demand.

Design is where you have the most influence at the least cost. A hesitant brief produces a house that has to be changed during construction, which is where it is most expensive.

  1. 1

    Choose an architect

    Check the architect’s registration with the Pakistan Council of Architects and Town Planners (PCATP), visit houses they have designed and speak to past clients. Agree the scope, the stages of the work and the fee in writing.

  2. 2

    Give them the brief, the plot in feet and the building limits

    Include the setbacks, coverage and floors from the authority. See the map approval guide.

  3. 3

    Review the concept

    Walk through the plan in your mind or on paper: from the gate to the door, from the bedroom to the bathroom, from the kitchen to the dining table. Check furniture will fit. Ask for sections and a 3D view.

  4. 4

    Appoint a structural engineer

    A registered engineer designs the foundation, columns, beams and slabs to the building code’s seismic provisions for your zone. Give them the soil information and the architect’s drawings.

  5. 5

    Get the services designed

    Electrical layout and load schedule, plumbing and drainage layout, septic or sewer connection, water tanks, and provisions for ACs and solar.

  6. 6

    Finalise the finishing schedule

    A schedule listing the finish of every room: floor, walls, ceiling, doors, windows, fittings. Without it, the finishing is decided on site, in a hurry.

The drawings to hold before you tender
Drawing setWhy you need it
Site planShows the house on the plot, with setbacks, gate and drains
Floor plans, elevations, sectionsThe design itself
Structural drawings and bar schedulesWhat the contractor builds and the inspector checks
Electrical layout and load scheduleCircuit design, cable sizes, points
Plumbing and drainage layoutPipe routes, fixtures, septic or sewer, tanks
Door and window scheduleSizes, materials and counts for the BOQ
Finishing scheduleChoice of materials for each room
Roof and waterproofing detailsSlopes, outlets, parapets and upstands
Chapter 5

Stages 4 and 5: approval and tender

Get the plan approved, and choose a contractor on a fair comparison.

Approval and tender can run in parallel to a degree, since the BOQ is prepared from the drawings while the authority reviews them. But do not award a contract or order materials until the stamped plan is in hand.

Approval

  • Find which body approves your plan, and whether a housing society also does.
  • Check the drawings against the setbacks, coverage, floors and parking before you submit.
  • Submit a complete pack, respond to objections in writing, and keep every letter.
  • Do not start work on a pending plan.

The full process, drawing set and rejection list are in House map approval in Pakistan.

Tender

  • Prepare a BOQ from the drawings, by someone who is not a bidder.
  • Vet three to five contractors by visiting their sites and calling past clients.
  • Issue the same package to each, hold a joint site visit, take questions in writing and answer all.
  • Compare the large items line by line, and find out why any rate is far from the others.
  • Choose on capability and terms as well as price.

See the cost guide for how to read and compare, and the contractor guide for the interview questions and tender steps.

Chapter 6

Stage 6: contract and starting the site

Sign a contract that protects both sides, and set the site up so you can see what happens.

The contract, the payment schedule and the inspection arrangements should be in place before the first trench. The full clause list is in the contractor guide. The short version is: milestone payments, a small advance, retention, hold points for inspection, written variations and a defects period.

Before the first shovel

0 of 12 done
Chapter 7

Stage 7: the grey structure

Know the order of the shell, and the hold point at which each stage is checked.

The grey structure is the shell: foundation, frame, slabs, walls and roof. Almost all of it is hidden later, so it is built in a sequence with a checkpoint before each part is covered. The details of every check are in the inspection guide; this is the order.

  1. 1

    Setting out and excavation

    Mark the house on the plot, excavate to the depth on the structural drawing, and confirm the ground. Checkpoint: setting out, then the excavation.

  2. 2

    Foundation

    Lean concrete, footing steel, concrete and curing. Checkpoint: the steel before the pour, and the pour itself.

  3. 3

    Columns up to plinth, plinth beam, DPC and anti-termite treatment

    The frame rises to plinth level, damp-proofing and termite treatment are applied, and the fill is compacted. Checkpoint: before backfilling.

  4. 4

    Ground-floor columns, beams and slab

    Steel and shuttering for columns, then beams and slab, with electrical conduits and sleeves placed before the pour. Checkpoint: before each pour. Cure for at least 7 days.

  5. 5

    Masonry

    Walls rise on the slab, tied to the columns, with openings and lintels. Checkpoint: openings, lintels and the quality of the work.

  6. 6

    Repeat for each upper floor

    The same sequence, with column starter bars ready, and the stair constructed with each floor.

  7. 7

    Roof slab, parapets, stair head (mumty) and tanks

    The roof slab carries the slopes, the outlets and the parapets that the waterproofing depends on. Checkpoint: slope and outlets before the waterproofing.

Chapter 8

Stage 8: services and waterproofing

Install and test the hidden systems before the walls and floors close over them.

Wiring, pipes, drains and waterproofing are the parts of a house that fail quietly, then expensively. Do them in the right order, and test each before it is covered.

  1. 1

    Electrical rough-in

    Conduits and boxes in the walls and slab, with the circuits, cable sizes and earthing as drawn. Run continuity and insulation tests.

  2. 2

    Plumbing and drainage rough-in

    Supply lines, drains, traps, vents and tanks, with a pressure test of the water lines and a flow test of the drains.

  3. 3

    Provisions

    AC drain lines and pipe sleeves, solar conduit, internet and TV cabling, and gas lines if used.

  4. 4

    Waterproofing

    Roof, bathrooms, kitchens, balconies and tanks, each with a flood test before the protective layer. See the waterproofing guide.

Chapter 9

Stage 9: finishing, and the order it must be done in

Know the sequence of the finishing work and the decisions that must be made before each part.

Finishing is where the house takes shape and where your choices have the biggest effect on the cost. The order matters: each layer must be dry and checked before the next goes on, and each decision has a latest date.

The usual finishing sequence
StepWorkWhy this order
1Plaster, after services are tested and window and door frames are fixedPlaster hides the wiring and pipes, so they are tested first
2Floor base and screed; waterproofing of wet areas, with flood testSlopes and waterproofing must be right before tiles
3Ceilings and false ceilings, if anyBefore the walls are painted, so there is no damage to the finish
4Wall and floor tilesAfter waterproofing; before fixtures
5Doors, windows and wood workAfter the plaster is dry
6First coat of paint (primer and putty)After the walls have dried
7Electrical fittings, sanitary ware, kitchen and wardrobesAfter the tiles and first coat, to avoid damage
8Final coats of paint and polishAfter the fixtures, in clean conditions
9Cleaning, snagging and final testsThe last step before handover

The decision calendar

Choices and the latest time to make them
DecisionNeeded beforeWhat goes wrong if late
Window and door sizes and positionsThe walls go upOpenings are cut after, which weakens the wall
Kitchen layout and appliance sizesPlumbing and electrical rough-inPipes and sockets in the wrong places
Bathroom fixtures and their positionsPlumbing rough-in and waterproofingThe drains and floor slopes do not fit
AC type, count and positionElectrical rough-in and the wall is closedNo power, drain or pipe route
Solar and backup designRoof waterproofing and conduitRoof penetrations after waterproofing; no conduit
Floor and wall tile selectionThe floor base is levelledLevels do not match the thickness of the tile
Ceiling design and lightsElectrical rough-inWiring not where the lights go
Wardrobe and cabinet layoutsPlaster is finishedSockets and switches behind a cabinet
Paint coloursThe first coatRepainting
Chapter 10

Stage 10: handover, completion and the first year

Close the job properly, collect the documents, and use the defects period.

  1. 1

    Do the snag walk-through

    Go through every room with a list, photograph every defect, and give the contractor the list with a deadline. Re-inspect each item.

  2. 2

    Run the final tests

    Water, drainage, electrical, ACs, pump and tank. Record the results.

  3. 3

    Collect the documents

    As-built drawings, approvals, test results, warranties, brand lists for finishes, utility documents and the contractor’s no-dues statement.

  4. 4

    Apply for the completion certificate

    To the authority that approved the plan, with the documents it asks for. You will need it for permanent utility connections in many places, and when you sell or borrow.

  5. 5

    Get the utility connections in your name

    Electricity, gas where available, water and sewerage, and make sure the meters work and the bills come to you.

  6. 6

    Hold the retention through the defects period

    Inspect the house after the first monsoon and again near the end of the period. Report defects in writing; release retention only when they are fixed.

Handover

0 of 10 done
Chapter 11

The ten mistakes that cost the most

Check your project against the errors that do the most damage, while they are still easy to avoid.

MistakeWhat it causesHow to avoid it
1. Buying a plot on the dealer’s wordA plot that cannot be built on or soldVerify at source; use your own lawyer. Guide
2. Designing to the wrong plot sizeRejected plans; paying for land you do not getWork in feet; check the marla definition
3. Starting before approvalNotices, fines, demolitionWait for the stamped plan. Guide
4. Tendering without a BOQQuotes you cannot compare; variations that growPrice a common BOQ. Guide
5. Choosing the lowest bid without asking whyCut corners or a contractor in troubleInvestigate outliers in writing
6. Large advances and payments by the calendarNo leverage; paying for work not doneMilestone payments. Guide
7. Not inspecting before things are coveredHidden defects found years laterHold points. Guide
8. Skipping the waterproofing testLeaks that mean breaking finished workFlood-test before tiles. Guide
9. Deciding finishes and services lateBreaking and re-doing; cost growthUse the decision calendar
10. No contingency and no recordsEvery surprise becomes a crisis or an argumentHold 10 to 15 per cent; keep a folder

Questions people ask

How long does it take to build a house?

It depends on the size, the design, the weather, the availability of labour and materials, and how quickly you decide. Approval can take weeks to months, the shell several months, and finishing several more. Agree a programme with your contractor, with dates for the main stages, and plan around the monsoon and the holidays.

Should I build the whole house at once or in phases?

Both work. If you phase it, say so at the start: the structural engineer must design the foundation and columns for the final number of floors, and the contractor must protect the shell and leave provisions for later work, so nothing built has to be broken.

Do I need an architect and an engineer?

You need a registered architect for the plan and a registered structural engineer for the structure. Many authorities require both for approval, and the structural design is what makes the house safe.

Should I buy materials myself?

Only if you can manage buying, storage, waste and quality, or have someone who can. A with-material contract on a BOQ is simpler for most owners, as long as the specification is clear and the work is inspected.

What should I do first?

Write the brief and set the budget, then choose and verify the plot. Everything else depends on them.

Can I do this from abroad?

Yes, with the right controls: a representative, evidence each week, independent inspection and payments tied to approved milestones. See building from abroad.

This guide is general guidance for building in Pakistan, last checked October 2026. Your approved drawings, your engineer's specification, the building regulations of your development authority and the law in force today take priority over anything written here. Fees, taxes and bylaws change: confirm current figures with the body that sets them.

Start with a Banao agent: verified architects and contractors bid for your project, and payments are held in escrow until each stage is approved.