Who this is for
- Owners deciding how much a house will really cost
- Owners holding two or three contractor quotes that do not look alike
- Anyone whose build is going over budget
Have to hand
- Draft drawings with dimensions, even if not yet approved
- A calculator, or a spreadsheet
- Quotes or rates from your own area, current this month
You will finish with
- A budget with every cost head and a contingency
- The method for calculating quantities from drawings
- A comparison table that makes quotes comparable
Why estimates fail
Understand the three mistakes behind most budget overruns, so you do not make them.
Most overruns have the same three causes. The estimate was for a smaller scope than the house you ended up building. It left out costs that sit outside the contractor’s price. And the finishing, which varies most, was decided late.
- 1
The scope was not defined
A “per square foot rate” means nothing unless you know what is in it. Is it grey structure only, or complete? Are doors, windows, tiles, sanitary ware, wiring, paint, kitchen and wardrobes in or out? Are the boundary wall, the water tank and the septic tank in or out? Two quotes at the same rate can be hundreds of thousands of rupees apart in what they include.
- 2
The area was measured differently
Covered area can include or exclude the walls, the stairs, the balconies, the porch, the mumty and the basement. Agree one definition, in the contract, and use it throughout.
- 3
Costs outside the build were forgotten
Design and approval fees, soil test, utility connections, boundary wall and gate, furniture, curtains, appliances and the cost of living elsewhere while you build are not in a contractor’s quote but are part of your cost.
- 4
Finishing was decided late
The structure is mostly steel, cement, sand, aggregate, bricks and labour, which can be measured from the drawings. The finishing depends on your taste, and the choices from basic to premium cover a very wide range. Deciding tiles and fittings during the build, in a hurry, is when budgets grow.
How to measure covered area
Covered area is the built area of each floor, measured to the outer face of the external walls. Roofed porches and car sheds are usually counted. Open balconies and terraces are usually counted at a fraction, and basements and mumties are separate lines. The share and the treatment vary from contractor to contractor, which is why you write the definition into the contract. Whatever you pick, apply it to every quote you compare.
Build the budget: every cost head, with a contingency
List every cost the project will produce, in the order you will meet them, and put a reserve on top.
Start with the money, not the design. Decide the most you will spend in total, including everything below. Then see whether the design you want fits. It is much cheaper to change a drawing than a building.
| Cost head | What it includes | When you commit it |
|---|---|---|
| Land and transfer | Price, taxes, transfer and legal fees | Before design |
| Design and approval | Architect, structural engineer, services design, approval fees, soil test, survey | Before construction |
| Grey structure | Excavation, foundations, columns, beams, slabs, stairs, masonry, roof, rough conduits and pipes | At award of the contract |
| Finishing | Plaster, floors, tiles, doors, windows, paint, wood work, sanitary ware, electrical fittings | Choices before the structure is finished |
| Services | Electrical, plumbing, drainage, gas, air-conditioning provisions, solar, water tank and pump, septic tank | Partly in the structure, partly in finishing |
| External works | Boundary wall, gate, driveway, drains, landscaping | Near the end, but boundary wall may come first |
| Utility connections | Electricity, gas, water, sewerage, internet: connection fees and deposits | Near the end, apply early |
| Supervision and testing | Site engineer, concrete cube tests, pressure tests | Throughout |
| Furniture and fittings | Kitchen, wardrobes, furniture, curtains, appliances | After finishing, but plan space and points early |
| Contingency | A reserve for things not yet known | Held until needed |
Budget check
0 of 8 doneThe quick estimate: a rate from real quotes
Use quotes to get a rough rate per square foot, and know how far to trust it.
A rate per square foot is a good way to see whether a design is in the right range, and a bad way to decide a price. It averages everything out, so it hides the differences that matter. Use it at the start, then replace it with a BOQ.
- 1
Collect recent quotes for similar work
Ask at least three reputable contractors for quotes on a similar house in your city this month. Ask for grey structure and finishing separately, and for a list of what is included.
- 2
Make the inclusions identical
Put the inclusions side by side. Add to or subtract from each quote so they cover the same scope. A quote that excludes doors and windows is not cheaper than one that includes them.
- 3
Divide by the same area
Rate = total price ÷ covered area, using your single definition of covered area.
- 4
Treat the result as a range
The rates will differ. A low outlier is a question, not a bargain. Use the spread of the sensible quotes as your range.
- Covered area: ground floor 1,200 sq ft + first floor 1,200 sq ft = 2,400 sq ft.
- Suppose grey structure quotes come to Rs 1,000 per sq ft, and finishing quotes Rs 1,200 per sq ft (numbers chosen to be easy to calculate).
- Grey structure = 2,400 × 1,000 = Rs 2,400,000.
- Finishing = 2,400 × 1,200 = Rs 2,880,000.
- Construction subtotal = Rs 5,280,000.
- Contingency at 10% = Rs 528,000.
Work out quantities from the drawings
Calculate the main quantities yourself, so you can check anyone’s BOQ.
A quantity is a measurement taken from the drawing: how much concrete, how much wall, how much plaster. You do not need to produce a full take-off to be useful. Working out the biggest items yourself shows you whether a contractor’s numbers are in the right range.
| Item | Unit | How to calculate |
|---|---|---|
| Concrete (footings, columns, beams, slabs) | Cubic feet | Length × width × depth of each element, added together. Convert inches to feet by dividing by 12 |
| Reinforcement steel | Kilograms | Total length of each bar size from the bar schedule × weight per metre (see the bar weights in the inspection guide) |
| Brickwork or block work | Cubic feet or square feet | Wall length × height × thickness, less the openings (doors, windows) |
| Plaster | Square feet | Wall length × height, on each face to be plastered, less the openings |
| Flooring and tiles | Square feet | Floor area of each room, plus extra for cutting waste |
| Paint | Square feet | Plastered wall area and ceilings |
| Excavation | Cubic feet | Length × width × depth of the trenches or pits |
| Doors, windows, fixtures | Number | Counted from the door and window schedule |
- A room slab is 20 ft × 15 ft and 5 inches thick.
- Thickness in feet = 5 ÷ 12 = 0.4167 ft.
- Volume = 20 × 15 × 0.4167 = 125 cubic feet.
- Add a small allowance for waste, for example 3 to 5 per cent: 125 × 1.04 = about 130 cubic feet.
- The bar schedule lists 100 bars of #4 (1/2 inch), each 12 ft long.
- Length of each bar in metres = 12 × 0.3048 = 3.66 m.
- A #4 bar weighs about 0.994 kg per metre, so each bar is 3.66 × 0.994 = 3.64 kg.
- Total = 100 × 3.64 = 364 kg.
- A wall is 20 ft long and 10 ft high and 9 inches thick, with one window of 4 ft × 3 ft.
- Gross area = 20 × 10 = 200 sq ft. Less the window: 12 sq ft. Net area = 188 sq ft.
- Volume = 188 × (9 ÷ 12) = 188 × 0.75 = 141 cubic feet.
- Plaster, on both faces = 2 × 188 = 376 sq ft (before adjustments for the reveals).
What a BOQ is and how it is organised
Know the parts of a bill of quantities, and what a good item description looks like.
A bill of quantities (BOQ) is a list of every item of work in the project, each with a description, a unit and a quantity. The contractor adds a rate to each, and the quantity multiplied by the rate gives the amount. The total is the price. Because every contractor prices the same list, the quotes can be compared item by item.
| Section | Items typically in it | Usual units |
|---|---|---|
| Preliminaries | Site setup, temporary water and electricity, insurance, cleaning, testing | Lump sum or per month |
| Earthwork | Excavation, backfilling, levelling, disposal of surplus soil, anti-termite treatment | Cubic feet, square feet |
| Concrete | Lean concrete, footings, columns, beams, slabs, stairs, lintels, with shuttering | Cubic feet, square feet of formwork |
| Reinforcement | Steel bars by size | Kilograms |
| Masonry | Brick or block walls by thickness, DPC | Cubic feet, square feet |
| Plaster | Internal and external plaster | Square feet |
| Waterproofing | Roof, wet areas, tanks, below-ground walls | Square feet |
| Floors and tiles | Floor base, tiles, skirting, wall tiles, stairs, thresholds | Square feet, running feet |
| Doors and windows | By type and size, with frames, glass and fittings | Number |
| Paint | Putty, primer and coats, internal and external | Square feet |
| Electrical | Conduit, wiring, switches, sockets, distribution board, earthing, fittings | Number, running feet, lump sum |
| Plumbing and sanitary | Pipework, fixtures, tanks, septic tank, drainage | Number, running feet |
| External works | Boundary wall, gate, driveway, external drains | Running feet, square feet |
| Provisional sums and contingency | Items not yet defined | Lump sum |
A good item description and a bad one
| Item | Poor description | Good description |
|---|---|---|
| Wall | Brickwork | Brick masonry in cement sand mortar 1:6, 9 inch thick walls, using first-class bricks, including curing and scaffolding, in cubic feet |
| Concrete | RCC slab | Reinforced concrete slab, specified strength or mix, 5 inch thick, including formwork, placing, vibrating and curing, in cubic feet; steel measured separately |
| Steel | Steel work | Grade 60 deformed steel bars, #4 and #5 by size, cut, bent, placed and tied as per the structural drawing, in kilograms, with mill certificates |
| Waterproofing | Roof treatment | Waterproofing membrane of a named type and thickness over a screed laid to slope, with turn-ups at parapets, tested by flooding, in square feet |
| Wiring | Electrical works | Copper wire of the stated cross-section for each circuit in PVC conduit concealed in walls, with breakers and earthing as per the electrical drawing |
The difference is that the good description says what, how thick, what grade, what is included and how it is measured. A contractor cannot quietly substitute a cheaper material if the description names the grade.
Checking a BOQ for what is missing
Read any BOQ for the gaps, the lump sums and the unbalanced rates that raise the final price.
Checking a BOQ
0 of 9 done| Item | Why it matters |
|---|---|
| Damp-proof course and anti-termite treatment | Cannot be added after the floor is down |
| Waterproofing of roof, bathrooms and tanks | Often left as an “extra”, then priced high when needed |
| Shuttering and scaffolding | A real cost; ask whether it is in the concrete rate |
| Curing of concrete and masonry | Skipped when it is not priced |
| Septic tank, soakage pit and external drains | Frequently left out of the grey structure price |
| Water tanks, pump and plumbing to the roof | Treated as the owner’s responsibility unless listed |
| Mumty (stair head room), parapets and railings | Measured as separate items or forgotten |
| Boundary wall and gate | Often a separate contract |
| Site clearing and removing debris at the end | A real cost that causes arguments at handover |
| Testing: cubes, pressure tests, flood tests | Needed for inspection, and not free |
Compare quotes line by line
Turn two or three different quotes into one table that shows which is actually cheaper and why.
- 1
Make every contractor price the same BOQ
The best method is to give the same BOQ, and the same drawings and specification, to all of them. Then the quantities are identical and only rates differ.
- 2
If they give their own quotes, convert them
Put each quote into a common table with the sections above. Where a contractor lumps several items together, ask them to split it.
- 3
Compare the big items first
Excavation, concrete, steel, masonry and plaster are usually most of the structure. Put the rate for each, side by side. This is where real differences show.
- 4
Investigate outliers in writing
A rate far below the others is a question: what material or workmanship is being cut? Ask for the answer in writing and for the brand, grade and mix to be added to the item.
- 5
Check the totals add up
Multiply quantity by rate on every line and add the amounts. Arithmetical errors in a quote are common and sometimes deliberate.
- 6
Compare terms, not just prices
Time to complete, payment schedule, retention, warranty and who supplies the materials all change what a quote is worth. See hiring and paying a contractor.
| Section | Contractor A | Contractor B | Contractor C | Notes |
|---|---|---|---|---|
| Excavation and earthwork | ||||
| Concrete (per cubic foot) | ||||
| Steel (per kg) | ||||
| Masonry | ||||
| Plaster | ||||
| Waterproofing | ||||
| Floors and tiles | ||||
| Doors and windows | ||||
| Electrical and plumbing | ||||
| Total, same scope | ||||
| Time to complete |
Controlling cost during the build
Keep the budget from growing, by managing changes, tracking money and knowing where saving is safe.
- 1
Treat every change as a priced variation
Before any change is built, get the contractor to price it in writing in the same style as the BOQ (a new item or a revised quantity), and approve it or not. Changes agreed verbally are the biggest source of disagreement at the end.
- 2
Replace provisional sums early
A provisional sum is a placeholder. As soon as you have chosen the tiles or the fittings, replace it with a real item and a real price. The longer it stays, the more it can grow.
- 3
Decide whether prices are fixed
In a time of changing steel and cement prices, a fixed-price contract is a protection for you, and a risk for the contractor. If prices can change, say how: which materials, what index or invoice, who pays. Do not leave it open.
- 4
Keep a simple cost report
Once a month: the budget, the amount committed, the amount paid, the forecast to complete and the contingency left. If committed is rising faster than the work is, find out why now.
- 5
Order finishing materials in good time
Choose tiles, sanitary ware and fittings before the structure is complete so lead times and prices are known and no one rushes a choice.
| Usually safe to save on | Never save on |
|---|---|
| A simpler elevation and roof shape | The amount, size or grade of reinforcement steel |
| Fewer different window and door sizes | Concrete mix, cover and curing |
| Standard rather than imported finishes | Waterproofing and the damp-proof course |
| Phasing finishing: structure now, upper floors later | Electrical cable size and earthing |
| A smaller built area or fewer bathrooms | Structural design and the foundation |
| Buying materials in bulk at a planned time | Inspection of the work |
Questions people ask
What is a reasonable rate per square foot?
It depends on the city, the month, the specification and what is included, so any figure printed here would soon be wrong. Get three current quotes for a similar house with the same inclusions and the same definition of covered area, and use their spread.
Should I pay the contractor a lump sum or by BOQ?
A BOQ-based contract (priced per measured quantity) shows you what you are paying for and makes changes straightforward. A lump sum for a well-defined scope can work, but only if the scope is itemised and attached. A lump sum for “the house” leaves you no way to judge a price or to price a change.
Is a labour-only contract cheaper?
The labour rate is lower, but you buy the materials, so you carry the risk of price changes, theft, waste and quality of what is bought. It works for owners who can manage buying and supervision. It is not a cheaper way to build the same house for an owner who cannot.
Who should prepare the BOQ?
Someone who can measure from the drawings: an architect, a quantity surveyor or a site engineer. It should be prepared by someone who is not the contractor who will build, so the list is the owner’s, not the bidder’s.
How much contingency should I hold?
Builders and engineers commonly advise around 10 to 15 per cent of the construction cost, and more where the design is incomplete, the soil unknown or the owner is away. Keep it separate from the main budget.
What if the bids are all much higher than my budget?
Go back to the BOQ and find where the money is. Simplify the design, phase the finishing or reduce the built area. Do not cut the structure, steel, waterproofing or inspection to hit a number.
This guide is general guidance for building in Pakistan, last checked October 2026. Your approved drawings, your engineer's specification, the building regulations of your development authority and the law in force today take priority over anything written here. Fees, taxes and bylaws change: confirm current figures with the body that sets them.
Get one BOQ prepared from your approved drawings, and have verified contractors price the same list.
Start your project, freeKeep going
- Before and during constructionHow to hire a contractor and pay without being burned
- While it is being builtHow to inspect a house build, stage by stage
- Services and systemsSizing a home solar system and comparing installer quotes
Shorter reads on parts of this: how to read a construction BOQ, grey structure vs finishing.